Enhanced Maintenance and Improvement EMI
Enhanced Maintenance and Improvement (EMI) refers to a programme strategy for refurbishment and restoration projects that involves a sequenced or staged approach to work on a rolling basis, allowing occupants to continue using a building as work are carried out. Whilst it can increase costs and timeframe dramatically it can also avoid the need for temporary accommodation and the disruption caused by vacation g a building for works to be carried out.
One example where the phrase is used is by the Restoration and Renewal (R&R) Programme for the refurbishment of the Palace of Westminster and which was originally established in 2013 by both of the Houses of Parliament. In their costed report Delivering restoration and renewal of the Palace of Westminster: the costed proposals published in 2026, EMI is discussed as one of three options for the refurbishment along with full decant; where both Houses move out for the works and continued presence; one House moves out for the duration of the works. The third option EMI is described thus:
"Enhanced maintenance and improvement (EMI): which has as an objective that not more than 30% of the Palace of Westminster (by usable area) would be decanted at any one time. The Palace of Westminster would be split into 14 zones which would be worked on in stages: functions of both Houses would be decanted for periods to facilitate this. Two variants of the EMI option have been assessed:
- i. EMI: this variant had the ambition of seeking to retain both Chambers in place throughout the Programme, with any work on the Chambers taking place in recesses and out-of-hours. The variant is set out in this report but following a recommendation by the Programme Board we recommend that it should not be further developed. It would have had a high cost together with the longest duration of any option; and
- ii. EMI+: under this variant, the House of Lords would be decanted for 8 to 13 years while the Commons, subject to the Lords’ agreement, would be decanted to the Lords Chamber for up to two years."
[edit] Related articles on Designing Buildings
- 10 Downing Street.
- 2020 IHBC Gus Astley Student Awards.
- Big Ben.
- City Hall, London.
- Demolishing Whitehall.
- Gothic revival style.
- Machicolation.
- Monument and context.
- Mr Barry's War.
- Nineteenth century building types.
- Oxford Movement.
- Palace of Westminster.
- Parliamentary procedure.
- Redesigning parliament to help end the Brexit deadlock.
- Restoration and Renewal.
- Restoring the Palace of Westminster's ventilation system.
- Scottish Parliament Building.
- St Pauls Cathedral.
- Strawberry Hill House.
- The Story of Kensington Palace.
- US Capitol Building.
Featured articles and news
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.